Chapter 6 Verifying the OneCell installation
6-2 913035 4.0.04 June 2019
DR
AFT
Overview
This chapter describes how to verify component installation and configuration and
make sure everything is operating properly after installation and configuration.(This
process is called commissioning.)
The tools used to verify the OneCell instal
lation are:
• Baseband Controller and Radio Point LEDs
• Baseband Controller Web GUI
• Ping tests
• User Equipment (UE) logs
Verify the OneCell system installation
To verify that the OneCell system installation is operating, check the Baseband
Controller LEDs. The STATUS, TIMING and CORE LEDs should be solid green.
For more information on troubleshooting the OneCell system
installation, see
Baseband Controller LED patterns on page B-2.
Figure 6-1. Baseband Controller front panel