User Manual
Table Of Contents
- Contents
- List of figures
- List of tables
- About this document
- ipBTS system overview
- Planning
- ipBTS C30 installation
- RN commissioning
- Requirements
- CLI connection
- Establishing a console connection
- Connecting the laptop to the ipBTS C30
- Downloading and activating new software
- Verifying SNTP time
- Commissioning the ipBTS C30
- Performing Loopback tests
- The loopback test process
- Backhaul loopback testing
- Ethernet loopbacks
- Looping back Ethernet backhaul links
- Looping back at the Ethernet port
- Entering diagnostic mode and configuring test parameters
- Performing external loopback tests on backhaul links
- Troubleshooting failed backhaul links
- Removing physical loopbacks
- Configuring IP on the Ethernet port and laptop
- Establishing the CLI/SSH/Ethernet connection
- Updating node software
- RN hardware components
- RN Specifications
- Hot-swapping ipBTS hardware
- Index
Chapter 3 l ipBTS C30 installation
Connecting to a power source
3-8 910136 Rev01.00 Standard July 2007
Figure 3-7. GPS connection - front of chassis
Figure 3-8. GPS connection - rear of chassis
Connecting radio module sector ports
The radio module has three SMA connectors per sector on the front and rear of the module.
Below the radio module there are matching SMA connectors in the chassis that are pre-wired
at the factory. This procedure connects the nine short jumper cables to the SMA connectors on
the front and rear of the chassis.
Procedure
1. Connect one end of a jumper cable to an SMA port on the radio module.
2. Connect the other end of the jumper cable to the SMA port on the chassis directly below
the first connection.
3. Repeat step 1 and step 2 for the remaining eight SMA connectors.
4. Use the torque wrench to tighten each SMA connector to 1 N-m (9 in-lbs).
Connecting to a power source
Before connecting the ipBTS to the -48V power source follow the instructions in this section to
verify that all pre-power up steps have been completed.
Pre-power on checklist
Before connecting and applying power to the ipBTS verify that the following tasks have been
completed:
ADCC front
Chassis rear