5 COMMISSIONING
5.1 PRE-COMMISSIONING TASKS
After equipment installation, perform the following steps before equipment powering and commissioning:
Prepare the channel frequencies.
Verify that the expected voltage, current and power levels do not violate any ratings.
Visually inspect the power connection within the equipment. Ensure that the power cable is correctly and securely
connected, including the grounding wire, RF cable and other cables.
Check the grounding connection and verify that the ground resistance is less than 5Ω.
Test the antenna system and ensure that the echo loss within working frequencies is less than -14dB (VSWR<1.5).
5.2 COMMISSIONING PROCEDURE
Perform the following procedures for system commissioning.
Table 5: Commissioning Task Explanation
Commissioning Tasks
Observation
1. Set filter frequencies
In Master Unit Device page or on each individual units’ page
Update the frequency for each filter in the device page
2. Go through commissioning
process
In Master Unit Commissioning page
Scan system elements
Update units’ information
Isolation test
Uplink Calibration
Downlink Calibration
3. Turn on 700/800MHz
switches, turn on filter
switches
In Master Unit Device page or on each individual units’ page
Turn on the switches for 700/800MHz and switches for each filter
4. Determine system downlink
gain and uplink gain for each
filter
In Master Unit Device page
Determine and set the downlink or uplink gain based on the downlink input
power / the link budget calculation or the design
5. Fine tuning the gain
In each individual units’ page
You must fine tune the gain individually on each unit
6. Alarm Setting Review
In Master Unit Management page or on each individual units’ page
Review the alarm setting for Donor Antenna monitoring, and for dry
contact alarms
End of Section