3.1. Initial Operation
Check whether the inlet of the drying hopper is closed by a blind lid, or whether a conveyor unit
(optional) is installed.
If not, manufacture a suitable blind lid and install it on the inlet of the drying hopper or install the
conveyor unit (optional).
F
Attachments which are not supplied by Colortronic must be manufactur
-
ed according to the safety regulation European Standard 294.
Check whether the coolant circuit of the return air cooler is turned on (if a return air cooler is instal
-
led).
3.1.1. Switching on the Dryer
Switch on the main switch of the dryer.
&
The signal lamp “power” goes on.
For operation with timer clock (optional):
Turn the release switch “Timer” at position:
For operation without timer clock:
Turn the release switch “Timer” at position:
&
The blower is running.
F
If the dryer has not been in use for several months it must be operated for
about 2 hours without material.
64.10-0214GB11 07/03
CTT 40 / CTT 70
Start up 3-2