Technical data
Insert the splash guard into the top hole of the gravity
feed tube
Lightly lubricate both orings on each tube with the
sanitary lubricant. When finished, place a feed tube
uninstalled at the bottom of each mix tank
Lubricate
7
The machine is now completely assembled and ready
to be sanitized
D)
Assembling the Mix Injection
Pump
Before assembling the mix injection pump, locate all of
the parts that will be required. (See Below)
First install the small or ing
(#3
1) onto the pressure
relief plunger (#105) and lightly lubricate the oring.
NOTE: Oring
#I126
is slightly smaller than the
other orings used on this assembly. Locate these
orings, first and install.
Assemble the connecting tube (#207) with the check
valve
(#3
1) and orings (#1126) and (#1117) Lightly
lubricate the check valve before installing into the
connecting tube. Lightly lubricate both orings
Install the two orings
(#1126) into the bottom grooves
of'the feeding elbows (#32) then lightly lubricate
Install the assembled pressure relief plunger into the
feed elbows, small end first Next install the assembled
connecting tube into the mix feed elbow, check valve
first The feeding elbows are now completely
assembled and can be placed into the bottom of the mix
storage tanks.