CENTER FOR ALLIED HEALTH AND ATHLETICS FF&E April 24, 2014
SECTION 27 41 00 AUDIOVISUAL SYSTEMS
Marshall Craft Associates, Inc. 27 41 00-9
Project 12032
d. Schematic drawings (AV & Control Signal Flow), system functional block
drawings, including those for audio and video subsystems. Resubmission of
contract drawings is unacceptable.
e. All unusual equipment modifications.
f. Front mechanical drawings of each equipment rack.
g. Equipment location drawings.
h. Cable labeling plan.
i. Floor Plans, RCPs and Elevations: Show planned location for all elements and
cable routing. Drawings should be at project standard scale and clearly legible.
D. Form
1. Submit all materials for review as described above, specifically referenced to the
Specification paragraph number (where applicable).
a. Submit all drawings on sheets of one size, preferably the project standard size.
b. Where materials are presented on sheets 11” x 17” or smaller, organize into
three-ring binder which include:
1) Dividersortabsbetweenlogicalsections
2) Projectnameandbindertitlelabelsonfaceandedgeofbinders
c. On submittal drawings, maintain 3/32” minimum lettering height. Submittals with
text less than 1/16” in height may be rejected.
2. Partial Submittals may be rejected. If submitted individually and each in its entirety, the
following Submittals shall not be considered partial:
a. Personnel
b. Milestones
c. Conduit Verification Statement and Notifications
d. Rigging and Mounting Drawings
e. As-Built Documentation
3. Product Data and Shop drawings must be submitted together in order to be reviewed.
E. User Interface
1. In order to develop a user interface which is both functional and useable, provide
working “Beta” copies of system software for review and comment by the owner,
architect and the AV consultant as per the below listed schedule:
a. This is anticipated to be an interactive process, requiring at least three submittals
prior to first beneficial use. At a minimum, the software development process will
have the following milestones:
1) InitialconceptSubmittalforReview
2) FirstBetaReview
3) SecondBetaReview
4) FinalI mplementationandOnSiteTraining:PriortoFinalAcceptance
5) Followup programming review and updates; Timing (within sixtydays from
finalacceptance)
F. Weekly Reporting