Specifications

Project #2008377 VIDEO PRODUCTION SYSTEM
Section 11130 (or 27 41 30)
Page 1
Video Production Redesign FBC Highland Park
Landover, Indiana
10/07/2013
GENERAL
1.1 GENERAL REQUIREMENTS
All requirements under Instructions to Bidders, General Conditions, Supplementary Conditions, Special
Conditions, Division One (1), Technical Specifications, Referenced Documents or Practices and any
Addenda of these Specifications shall be a part of this section. Each Contractor is responsible to be
thoroughly familiar with all its contents as to requirements which affect this Division or Section. Coordinate
all items with Owner to insure that all items are furnished in accordance with Owner standards.
1.2 RELATED DOCUMENTS
AV Drawings
27 41 36 - Sound Reinforcement System
1.3 REFERENCES
National Fire Protection Association (N.F.P.A.).
American National Safety Institute (A.N.S.I.).
National Electrical Code (N.E.C.).
Underwriters Laboratories (U.L.)
Electronics Industries Association (E.I.A).
National Cable Television Association (N.C.T.A.)
Society of Motion Picture and Television Engineers (S.M.P.T.E.)
International Telecommunications Union (I.T.U.-T.)
CCIR 601
EIA RS-170A
1.4 RESPONSIBILITY AND RELATED WORK
The written specification and drawings AV0.00 through AV7.59 shall be collectively referred to herein as
the Contract Documents.
The systems described in this section will be called the “Production Systems” and the installer will be named
“The Contractor.” The Contractor will provide all labor, materials, equipment, necessary tools, test
equipment, hoisting, transportation, supervision and coordination necessary to complete the installation of
the “Production Systems” as described in these specifications and illustrated on the Project drawings.
Contractor shall provide, based on the Contract Documents, a complete, turnkey system, tested and ready
for acceptance testing. The Contract Documents are developed to the extent required to properly convey
design intent, signal flow, and system infrastructure. It is understood by the contractor that they are to
supply additional equipment, as required, in order to provide a complete and working system.