Specifications

Intelligent Building Series C-Touch Programming Reference
If the Schedule is to be executed on particular days of the month,
then the required days are selected. There are buttons at the bottom
to allow:
all days to be selected quickly,
all days to be cleared quickly,
the first week of the month etc. to be selected.
If the Schedule is to be executed in particular months, then the
required months are selected. There are buttons at the bottom to
allow:
all months to be selected quickly
all months to be cleared quickly.
If the Schedule is to be executed in a particular year, the Any Year
check box is deselected and the year required is selected from the
scroll box.
The Days, Months and Years can be combined in any combination.
So for example, if the Schedule is to occur on the first Tuesday of
every month, Tuesday is selected along with the first 7 days of the
month. (This ensures that the Tuesday in question is contained within
those first seven days).
Event
An event is an action that will occur at a scheduled time and day. There
are three choices: setting a Group to a particular level, pulsing a group or
setting a scene.
The Ramp Group button can set a group to be ramped. To set a ramp
operation, the required group, level and ramp rate must be selected.
The Pulse Group button can set a group to be pulsed (ie. set to a
particular level for a certain time). To set a pulse operation, the required
group, level, ramp rate, duration and return level (the level returned to at
the termination of the pulse) must be selected.
The Set Scene button can set a scene. To set a scene correctly the
required scene must be selected from the list.
When all changes are complete, the OK button finishes the programming.
The Cancel button causes an exit without making any changes to the
Schedule.
7.6.3 Schedule Monitor
The Schedule Monitor allows the user to see all schedules in a project,
and to see which are active.
The Schedule Monitor dialogue is invoked by selecting
Edit | Schedule | Schedule Monitor.
The Schedule Monitor is shown below. One button runs the scheduler (the
icon with the clock), and the other runs the Schedule Manager (the icon
with the notepad).
© Copyright 2002 Clipsal Integrated Systems Pty Ltd Page 40