Pressure and Temperature Log
A log of temperatures and pressures should be taken regularlyPeriodically conduct a visual inspection of the chiller to identify problems before
they reach the point of failure As with any mechanical system, it is necessary to conduct a series of checks to the ClimaCool chiller to conrm
correct operation
Weekly
Review daily log from previous week
Perform visual inspection
Properly document all data taken
Note any problems that may existImmediately plan for further
investigationIf repair is necessary, schedule for earliest possible
date
Monthly
Extract a water sample from the evaporatorConrm that the sample
bottle is lled to the top leaving no air in the bottle Sample to be
tested and kept in compliance with the water quality parameters
listed in Table 1 on the water treatment page of this manualNOTE:
Monthly records of compliance and testing are required throughout
the warranty period for warranty
Quarterly
Check controller operating parameters and set points
Check refrigerant pressures and temperatures
Check compressor amps
Check compressor oil level
Check and test all safeties
Check water ow rates and pressure drops across evaporator and
condenser
Properly document all data taken
Annual
Isolate chiller, drain all water circuits
Backush all heat exchangers (use only ClimaCool
recommended de-scalers)
Remove and clean all waterside strainers
Perform leak test on all refrigerant circuits
Check all interconnecting anges for proper tightness
Perform oil analysis on each compressor
Check and test all refrigerant safeties for proper operation
Check all electrical terminal connections for tightness
Manually operate all waterside isolation valves on each module
Check all peripheral systems for proper operation
Check and test main controller
Verify set points, sensors and general conguration
Properly document all data taken
Recommended Maintenance Schedule
Daily
A daily operational log should be kept
Perform visually inspection
Record entering and leaving chilled water and condenser water
temperatures and pressures
Note any problems that may existImmediately plan for further
investigationIf repair is necessary, schedule for earliest possible
date
Properly document all data taken
Date _______ Data Log ___________________
Chiller No.
_____
Technician
___________________
Sun. Mon. Tue. Wed. Thu. Fri. Sat.
Chilled Water
Entering Temp.
Chilled Water
Leaving Temp.
Condenser Water
Entering Temp.
Condenser Water
Leaving Temp.
Chilled Water
Pressure Drop
Condenser Water
Pressure Drop
Faults: Note By
Module Number