Filling The Water System
FILLING THE WATER SYSTEMS
It is imperative that the water systems are free from debris
prior to initial operation See the Water Treatment section for a
comprehensive list of precautions
Filling, Purging and Leak Testing the System
After the water systems have been properly installed a visual
inspection should be made to all joints for tightness If the chiller
is to be installed in an existing system, the cleanliness of the
existing system can be judged from the operating conditions of
the present machines The cooling tower in particular, should be
inspected and cleaned if required It is a good practice to at least
ush the existing system and ideally, to acid wash the system
before connecting a new chiller
We recommend the following sequence to ll and leak check the
water systems:
1 Close all isolation valves inside each modular chiller
2 Ensure that all drain valves are closed and that all water main
isolation valves are opened
3 The system should be lled with clean water send through a
strainer and the system checked for leaks
4 Once the main water lines and the chiller headers are lled
with clean water, purge and repeat the lling process several
times
5 Open the isolation valves inside each modular chiller and
repeat the lling process, this time also checking for leaks
inside each module
6 Following the nal lling and leak checking procedure, air
should be purged from the system
Cleaning the System
We recommend the following sequence to properly clean the
water systems:
1 If possible, install a temporary bypass line between the supply
and return water lines of both water systems prior to cleaning
the system
2 Close all isolation valves inside each modular chiller before
engaging the main water pumps
3 The pumps should be run with the strainer in place (see the
Starting the Pumps section for proper pump startup) All
external hydronic branches should be open to all devices in
the system
4 After several hours of operation, the strainer should be
isolated and cleaned
5 Step 4 should be repeated until there is no more debris being
collected by the strainer
6 Finally, open all isolation valves inside each modular chiller
and repeat step 4 and 5
If it is not possible to install the bypass line in step 1 above, it is
recommended to drain out the initial ll of water to help ush out
debris The chiller isolating valves should be closed to prevent
debris from being washed into the chiller as the water drains out
Before relling and purging the system again, the strainers should
be removed and cleaned This action should be repeated until
there is no more debris being collected by the strainer
Starting the Pumps
Follow manufacturer’s recommendations when starting the
pumps for the rst time The system should be checked for leaks
and air purged with the pumps in operation The pressure drop
across the heat exchangers will give a good indication of ow
through the system (see page 35) This should be immediately
checked against the expected pressure drop for the ow rate
required If the pressure drop begins to fall and the ow rate is
falling, this could indicate the need to clean the strainers