Technical data

TraverseEdge 2020 Applications and Engineering Guide, Chapter 3: System Applications
Page 3-12 Turin Networks Release 5.0.x
For physical layer module part numbers and availability, refer to the TE-2020 Ordering Guide
(WR-D2020-ORD-050000).
For detailed physical descriptions of the modules, refer to the TE-2020 Hardware Description
Guide (WR-D2020-HWD-050000).
3.2.3 Terminal Node with an OTS2
Figure 3-13 shows a 1+1 terminal configuration with a full 16 protected OC-12 signal drop capability. This
configuration requires only four rack units of space.
Figure 3-13 OC-192 1+1 Terminal Configuration with 16 Protected OC-12 Drops
Table 3-4 Terminal Shelf with DS3/EC-1 Equipment Requirements
QTY Part
1 TE-2020 Main Shelf
2 TE-2020 Main CCT
1 TE-2020 Main Fan
2 OC-192 x1 PLM
4 ETS1 Shelves
8 ETS1 Tributary CCT
4ETS Fan Tray
4 Local Equipment Interconnect Cable Pair
20 DS3/EC1 PLM (twelve port)
4 Optical PLM Blanks