4 Pre-Installation Checklist
4.1 Inventory Check
Make sure that all the units are present
Check the containers to make sure they were not mistreated or damaged
Inspect the MCT’s for any distortions such as:
o Shattered Glass
o Cracks
o Obvious Bends
o Collapsed/Bent Terminals
4.2 Site Layout Checklist
Make sure that there is Unistrut mounted on the roof
Check to make sure the pitch between the Unistrut is correct
Consult the Roof Design Layout provided by the supervising engineer and check to see
that the spaces between banks (side to side as well as front to back) are correct
Check to see that the length of strut provided will be able to mount the required
number of panels