Specifications
Preparing to Install a System
1-6 Stratus ftServer V 2302, V 4304, and V 6308 Systems: Site Planning Guide (R624)
NOTE
Depending on the system configuration and the
components you have ordered, a separate carton
containing components may be shipped with your system.
When your system arrives, do the following:
• Contact the CAC or your authorized Stratus service representative.
• Check the Tip-N-Tell and Shockwatch motion sensors to determine if they have
been activated. If a sensor has been activated, or if there is any damage, report it
immediately to the carrier and to the CAC or your authorized Stratus service
representative.
• Check the packing list. If you received the wrong shipment, or if the shipment is
incomplete, report it immediately to the carrier and to the CAC or your authorized
Stratus service representative.
Moving the System to the Installation Site
Before moving your system to the installation site, do the following:
NOTE
Moving a system requires two able-bodied persons.
1. Obtain a forklift or pallet jack to move your system from the delivery area to the
installation site.
2. Check the dimensions of doorways and the load capacities of floors and elevators.
You should walk the path over which you will move the system to ensure that it can
be easily moved to the installation site. If your system will not fit through the
doorways, you may need to arrange for rigging.
NOTE
Each cabinet is shipped on a pallet that is slightly larger
than a standard door opening. A standard door opening is
35 in. (89 cm) wide, and all pallets are 41.0 in. (104.2 cm)
wide by 53.0 in. (134.6 cm) deep.
3. If you are moving the system across a raised floor, lay plywood on the raised floor
to prevent floor tiles from popping up when you move the system.
4. Move the system as close to the installation site as possible.