Specifications

PG1A, PG2A Installation Instructions
8
Figure 8
5. Close the hinged door on the projector guard and reinstall
the two security screws which were removed in Step 1 of
Configure Fillers on the Projector Guard.
6. Install four 10-24x3/8" security screws (G) in remaining four
holes. (See Figure 8)
NOTE: A padlock may be placed on the projector guard for
added security. (See Figure 9)
Figure 9
Install Projector Guard Using a Pipe Clamp
NOTE: Installation using a 1" or 1-1/2" diameter Schedule 40
steel pipe with 1-1/2" NPT threads requires securing
the pipe to the building structure. We suggest using a
CMA ceiling plate to secure the pipe to a structural
member.
1. Using the projector, security mount and NPT pipe,
determine the height location to install the locking collar (top
of security mount).
2. Install the clamp and fasteners as follows:
a. For 1-1/2" NPT install the clamp at the desired
height and secure using the U-bolt, two flat
washers, two lock washers, and two 5/16-18 hex
nuts (provided with U-bolt). (See Figure 10)
Figure 10
b. For 1" NPT install the clamp at the desired height and
secure using the U-bolt, two nylon spacers, two flat
washers, and two 5/16-19 hex nuts (provided with U-
bolt). (See Figure 11)
3. Install the projector on the 1" or 1-1/2" NPT pipe.
Figure 11
4. Slide the projector guard over the clamp assembly and
select the desired mounting slots in the projector guard.
5. Secure the projector guard to the clamp using two 1/4-20 x
3/4" buttonhead screws and two flat washers. (See Figure
11)
NOTE: A padlock may be placed on the projector guard for
added security. (See Figure 9)
x 4
Projector
Guard Slots
(H) x 4
(P) x 4
(K) x 4
6
(G) x 4
Insert
padlock
(F) NPT Pipe
(C)
(L) x 2
(J) x 2
Provided
with U-bolt
(F)
NPT Pipe
(C)
(L) x 2
(M) x 2
Provided
with U-bolt
5
x 2
(H) x 2
(K) x 2