Installation Guide Part 1

NGL FX Installation Manual Rev. *
18 of 84
Based on the outcome of the dry run test (i.e. the level of noise when simulating an unshielded
system), the decision is made to test with a Shielded FX system or continue with the installation
(if results indicate it will perform optimally in the environment). To simulate Shielded FX system
operation, the entire antenna assembly (floor panel) is placed on the floor. Testing occurs as before.
Site Survey Conclusion
Overall, the site survey is an opportunity to gather details and share information required for the
proper installation workflow. Before leaving the test site, the location of the remote electronics,
conduit cuts and their layout (plans with exact dimensions), floor cuts or pre-installation space
requirements (see diagrams found in the “Physical Installation” sections), power outlet locations
(or hardwire into electrical). Coordinating with contractors facilitates easier installation.
Note*: It is strongly suggested for any new construction that the transmission line be ran through
conduit. Communicate with the contractor (or store personnel) before concrete has been poured.
Ensure wire run does not exceed the maximum distance to the electronics’ planned location. This
crucial action will allow the transmission line cable to be easily routed through the conduit.