Installation manual
B-2
ChargePoint® Charging Stations
Power Share - Overview of Steps
1. Install jumpers and connect the wiring
2. Apply the Electrical Rating label
3. Complete the station installation (for new installations)
4. Enable Power Share
Power Share - Step by Step Instructions
Step 1: Install jumpers and connect wiring
WARNING: Disconnect power before you begin.
Push the black tab on the terminal block to release the terminal block cover, then slide the cover up until it locks
into the raised position:
Insert the jumpers into the slots located near the upper edge of the terminal block. Using a large flat blade
screwdriver, push firmly on each jumper until you feel it lock into place.
1/8”
3 mm
1/2” (13 mm)
IMPORTANT: Ensure both jumpers are
fully seated. The jumpers should recede
1/8” (3 mm) below the outer surface of the
terminal block, as shown. If they are flush,
they are not fully inserted.
Strip wires ½” (13 mm).