Installation manual
B
B-1
CT4000 Power Management Instructions
As shipped, a CT4000 charging station provides up to 30A of output power to each charging port. The Power Management
Kit (ordered separately) provides two features that you can use to adjust the station’s output power:
• Power Share allows both ports on a dual-port station to share a single circuit. In a default configuration, a dual-port
CT4000 requires two 40A circuits. WIth Power Share, both ports can share one circuit.
• Power Select allows the station to operate at a lower current. When the total current capacity is less than the standard
30A per circuit, you can use Power Select to configure the station to operate at a lower current.
Before you start
Before using the Power Management Kit:
• Refer to the site design to determine the charging station’s power requirements.
• Install the charging station’s main body as described in Chapter 2 (Bollard Mount) or 3 (Wall Mount). If you are
configuring Power Share, do not connect the wiring—you will first need to install the jumpers as described on
page B-2.
IMPORTANT: To configure Power Select, the station must be running software version 4.1.3 or later. To verify software
version, power up the station and display the station’s Service Menu as described on page B-3. Press the station button
immediately below the “HELP” menu option, then press the station button immediately below the “DOWN” menu option
to highlight “About”, then press “SELECT”. If a previous version of software is installed, call ChargePoint Customer
Support at 1-877-850-4562 so they can upgrade the station’s software.
Kit Contents
Jumpers (2)
(Required for Power Share)
Electrical Rating labels
(Whenever you change the station’s default power configuration,
you must apply a new label to the terminal block cover)