3-10
ChargePoint® Charging Stations
Step 9: Check Voltages
• Turn power ON.
• Using a solenoid type voltage tester, check that the
voltages at the charging station’s terminal block are as
follows:
Measure Between Volts
L1 and L2 208/240
GND and L1 120
GND and L2 120
If the voltages are not as expected, ensure that the
wiring has been properly connected as describing
on the previous page. For detailed wiring diagrams
and grounding requirements, see pages 1-4
to 1-6.
Before continuing, resolve any wiring issues and ensure
that voltages are as expected.
• Turn power OFF.