3-3
Installing a Wall Mount
Step 2: Drill Holes in Wall
• The packing box for the brackets is used as a
template for drilling the wall holes. Tear the packing
box along the perforation to allow it to lay flat.
• Place the template against the wall. As described on
the package insert, align the top where indicated, 49”
above the floor or ground. Ensure that the template
is level and the side of the packaging insert is plumb.
Mark the four mounting holes.
• Drill four holes in the wall at the marked locations.
NOTE:
• If mounting to a hollow wall, bridge at least two
studs using a 1 5/8” channel strut. For wood studs,
use 3/8” (9.5 mm) lag bolts that are long enough to
penetrate at least 2 1/2” into the stud. Then mount
the supplied brackets to the channel strut using 3/8-
16 x 1” long bolts, 3/8 ID x 13/16” OD washers, and
3/8-16 channel strut nuts.
• If mounting to a masonry wall, use 3/8” (9.5 mm)
expanding masonry fasteners.
• If mounting to a wood wall, use 3/8” (9.5 mm) x 3”
(76 mm) lag bolts.