Installation Manual
Table Of Contents
- Front Cover
- Table of Contents
- Introduction
- Installing a Bollard Mount
- Installing a Wall Mount
- Installing the Head and Top Cap
- Preparing the Station for Activation on ChargePoint
- Troubleshooting
- Appendix A: Preparing the Installation Site for a Bollard Mount
- Appendix B: Removing or Replacing the EV Charging Sign
- Appendix C: CT4000 Power Sharing Instructions
- Appendix D: Limited Product Warranty
2
2-1
Installing a Bollard Mount
Before You Start
Before installing a bollard mount, prepare the installation site as described in Appendix A. After preparing the installation site,
you need the following:
• Ratchet and 3/8” socket
• 1/2” drive torque wrench and 15/16” 6-point deep socket (for 5/8-11 nut)
• Crescent wrench
• Bubble level
• #2 Phillips screwdriver
• Wire stripper
• Multimeter
Overview of Steps
Installing the bollard mount involves a few simple steps, summarized below and detailed in the remainder of this chapter:
1. Check Boxes for Correct Contents (page 2-2)
2. Prepare Pole/Base Plate for Mounting (page 2-3)
3. Mount Pole/Base Plate (page 2-4)
4. Install Main Body (page 2-5)
5. Prepare Retractor for Mounting (page 2-6)
6. Install Retractor (page 2-7)
7. Connect Wiring (page 2-8)
8. Check Voltages (page 2-9)
When you have completed these steps, you will be ready to install the head and top assemblies as described in Chapter 4.