Installation manual

A-1
A
Preparing the Installation Site
for a Bollard Mount
Before You Start
The ChargePoint® Charging Station’s bollard mount can be installed either:
• into the ground
• onto an existing concrete surface (on an intermediate floor only)
The kit components you need to use, the tools required, and the installation steps vary depending on the type of installation.
This appendix provides basic guidelines for both types of installations.
IMPORTANT: Always check local codes to ensure compliance. You may need to adjust the guidelines provided in this
appendix to comply with codes that apply at your installation location.
Installation Overview
To install the CT4000 bollard mount into the ground, you will need the components shown below. These components can be
purchased from ChargePoint by ordering a CT4000 Concrete Mount Kit.
” - 11 x 9” F1554 Grade
55 hot-dipped galvanized
threaded bolts (3)
” - Heavy Galvanized Hex Nuts
(DH Rated) (12)
Galvanized Washers (ASTM F436) (9)
Plastic Bolt Installation Template (1)
CT4000 Installation Template
with CMK Footprint (1)
*NOTE: When installing onto an existing concrete surface, you will need only 6 Galvanised Hex Nuts and 6 Galvanised
Washers. But you will need several consumables as described on page A-3.