Installation Instructions
21
Wired setup
Before digging, contact local underground utility locating companies. Use
PVC conduit to prevent damage to cables.
1. Disconnect ALL power to the operator and turn OFF the battery
switch.
2. Trench across driveway to bury the shielded twisted pair cable.
3. Connect the wires from the shielded twisted pair cable to the Com Link
terminals on the primary gate operator control board. NOTE: We
recommend that all accessories and board configurations are set on
the primary operator.
4. Route the shielded twisted pair cable to the secondary gate operator's
control board.
5. Connect the wires from the shielded twisted pair cable to the Com Link
terminals on the secondary control board (Com Link A to Com Link A
and Com Link B to Com Link B). Ground the shield of the cable to the
chassis ground of one operator.
6. Connect ALL power to the operator and turn ON the battery switch.
DUAL GATE WIRE TYPE (SHIELDED TWISTED PAIR CABLE)
22AWG up to 200feet (61m) 18AWG - 200-1000feet (61-305m)
Wire must be rated at 30 Volt minimum
Com Link Data A
Com Link Data B
Com Link Data A
Com Link Data B
Bipart delay/synchronized close
The LOCK/BIPART DELAY switch is used only with dual gate applications and serves two functions:
l
BIPART DELAY
Not applicable for slide gate applications.
l
SYNCHRONIZED CLOSE
To synchronize the closing of the gates, set the LOCK/BIPART DELAY switch to ON for both operators.