The commissioning and acceptance procedure verifies the correct installation and the
proper, safe, and robust operation of the FibeAir 70 RF link.
Topics covered here include:
• ODU installation verification and testing
• Operational status of the link
• Acceptance tests to be performed on the link
• FibeAir 70 Commissioning and Acceptance Form
4.6 Installation Verification and Testing
Inspect the following components and confirm their a
dherence to requirements that are
detailed in the accompanying checklist, FibeAir 70 Commissioning and Acceptance Form
(Section 4.7).
Hint:
Make copies of the FibeAir 70 Commissioning and Acceptance Form and
use it as a comprehensive guide to RF link commissioning and acceptance.
4.6.1 Physical Installation Verification
This inspection verifies the physical installation o
f the ODU, in accordance with Chapter 2 of
this manual.
• Pole mount installation
• ODU installation
• Connectors’ sealing
• Cables installation
• Grounding