The commissioning and acceptance procedure verifies the correct installation and the
proper, safe, and robust operation of the FibeAir 70 RF link.
Topics covered here include:
ODU installation verification and testing
Operational status of the link
Acceptance tests to be performed on the link
FibeAir 70 Commissioning and Acceptance Form
4.6 Installation Verification and Testing
Inspect the following components and confirm their a
dherence to requirements that are
detailed in the accompanying checklist, FibeAir 70 Commissioning and Acceptance Form
(Section 4.7).
Hint:
Make copies of the FibeAir 70 Commissioning and Acceptance Form and
use it as a comprehensive guide to RF link commissioning and acceptance.
4.6.1 Physical Installation Verification
This inspection verifies the physical installation o
f the ODU, in accordance with Chapter 2 of
this manual.
Pole mount installation
ODU installation
Connectors sealing
Cables installation
Grounding