Specifications

130 SEBU7858-03
Maintenance Section
Ejector Carrier Rollers - Inspect/Pack/Replace
6. Repeat Step 3 th
rough Step 5 in order to adjust
the other ejector carrier roller.
7. Start the engi
ne.
8. Move the ejector forward and backward.
9. Stop the engine.
10. Check for dr
ag between the ejector and the
bottom of the bowl. Repeat the adjustment
procedure, if necessary.
i02444688
Ejector Carrier Rollers -
Inspect/Pack/Replace
SMCS Code: 6229-040; 6229-086; 6229-510
S/N: DBZ1-Up
g00920884
Illustration 160
Two ejector carrier rollers are located at the b ase of
the ejector.
1. Park the machine on level ground. Engage the
parking brake.
2. Lower the bowl and the apron to the ground.
3. Remove the debris from each roller in order to
inspect the rollers.
4. Pack the bearings of the rollers.
Reference: Machine Systems Disassembly and
Assembly, “Roller (Ejector Carrier)”
Reference: Hydraulic System Specications,
“Ejector”
i02501049
Ejector Guide Ro llers -
Check/Adjust
SMCS Code: 6230-025; 6230-535
S/N: DBZ1-Up
g009205
96
Illustration 161
The ejector guide rollers are located at the middle
of the ejector. There are two ejector guide rollers.
These r
ollers prevent the ejector from contacting the
sides of the bowl. These rollers prevent the ejector
from cocking.
1. Park the machine on level ground. Engage the
parking brake.
2. Lower the bowl to the ground and close the apron.
3. Check
the adjustment for the ejector guide rollers.
The ejector guide rollers are correctly adjusted if
the ejector does not contact the sides of the bowl.
The r
ollers should be in a position that prevents
the ejector from rising too far above the oor of
the bowl.
4. Loosen roller shaft clamping bolt (1).
5. Mov
e eccentric roller shaft (2) to a position that
allows the ejector to pass over the sides of the
bowl.
6. Tighten roller shaft clamping bolt (1).
7. Re
peat Step 4 through Step 6 in order to adjust
the other ejector guide roller.
8. St
art the engine.
9. Move the ejector forward and backward.
10. Stop the engine.