Specifications
B. Preliminary Equipment Check
IS THERE ANY SHIPPING DAMAGE? IF SO, WHERE
WILL THIS DAMAGE PREVENT UNIT START-UP?
M UNIT IS LEVEL IN ITS INSTALLATION
M UNIT IS SUPPLIED WITH THE PROPER CONTROL VOLTAGE
VAC
M ELECTRICAL CIRCUIT WIRING HAS BEEN SIZED AND INSTALLED PROPERLY
M UNIT GROUND WIRE HAS BEEN CONNECTED
M ELECTRICAL CIRCUIT PROTECTION HAS BEEN SIZED AND INSTALLED PROPERLY
M ALL TERMINALS ARE TIGHT
M ALL CABLES AND THERMISTORS HAVE BEEN INSPECTED FOR CROSSED WIRES
M ALL PLUG ASSEMBLIES ARE TIGHT
CHECK AIR-HANDLING SYSTEM
M ALL AIR HANDLERS ARE OPERATING
M ALL CHILLED WATER VALVES ARE OPEN
M ALL FLUID PIPING IS CONNECTED PROPERLY
M ALL AIR HAS BEEN VENTED FROM THE SYSTEM
M CHILLED WATER PUMP (CWP) IS OPERATING WITH THE CORRECT ROTATION
CWP AMPERAGE: RATED:
ACTUAL:
PUMP PRESSURES: INLET: OUTLET:
CHECK CONDENSER SYSTEM (30HX ONLY):
M ALL CONDENSER WATER VALVES ARE OPEN
M ALL CONDENSER PIPING IS CONNECTED PROPERLY
ALL AIR HAS BEEN VENTED FROM THE SYSTEM
M CONDENSER WATER PUMP IS OPERATING WITH THE CORRECT ROTATION
CONDENSER WATER PUMP AMP: RATED:
ACTUAL:
PUMP PRESSURES: INLET: OUTLET:
CHECK REMOTE CONDENSER SYSTEM (30HXA ONLY):
M ALL CONDENSER PIPING IS CONNECTED PROPERLY
M CONDENSER LINES/CONDENSER HAS BEEN EVACUATED, AS REQUIRED