Phau Ntawv Qhia
Table Of Contents
- Installation Instructions
- Safety Considerations
- Introduction
- Heater Packages
- Installation
- Check Equipment
- Mount Unit
- Nuisance sweating may occur if the unit is installed in a high humidity environment with low airflow.
- Downflow Installation
- Horizontal Installation
- A07565
- Fig. 2 – Slope Coil Unit in Upflow Application
- Horizontal Right Conversion of Units with Slope Coils
- 1. Remove blower and coil access panels and fitting panel (Fig. 6).
- 2. Remove coil mounting screw securing coil assembly to right side casing flange.
- 3. Remove coil assembly.
- 4. Lay fan coil on its right side and reinstall coil assembly with condensate pan down (Fig. 5).
- 5. Attach coil to casing flange using previously removed coil mounting screw.
- 6. Make sure pan cap in fitting door is properly seated on fitting door to retain low air leak rating of the unit.
- 7. Add gaskets from kit.
- 8. Align holes with tubing connections and condensate pan connections. Reinstall access panels and fitting panel.
- 9. Make sure liquid and suction tube grommets are in place to prevent air leaks and cabinet sweating. Install grommets after brazing.
- Horizontal Right Conversion of Units with A-Coils
- 1. Remove blower and coil access panels (Fig. 6).
- 2. Remove metal clip securing fitting panel to condensate pan. Remove fitting panel.
- 3. Remove 2 snap-in clips securing A-coil in unit.
- 4. Slide coil and pan assembly out of unit.
- 5. Remove horizontal drain pan support bracket from coil support rail on left side of unit and reinstall on coil support rail on right side of unit (Fig. 8).
- 6. Convert air seal assembly for horizontal right.
- a. Remove air seal assembly from coil by removing 4 screws (Fig. 6).
- b. Remove air splitter (B) from coil seal assembly by removing 3 screws (Fig. 7 inset).
- c. Remove filler plate (A) and install air splitter (B) in place of filler plate.
- d. Install filler plate (A) as shown in horizontal right application.
- e. Remove condensate troughs (C) and install on opposite tube sheets.
- f. Install hose onto plastic spout.
- 7. Install horizontal pan on right side of coil assembly.
- 8. Slide coil assembly into casing. Be sure coil bracket on each corner of vertical pan engages coil support rails.
- 9. Reinstall 2 snap-in clips to correctly position and secure coil assembly in unit. Be sure clip with large offsets is used on right side of unit to secure horizontal pan.
- 10. Remove two oval fitting caps from left side of the coil, access panel, and fitting panel.
- 11. Remove insulation knockouts on right side of coil access panel.
- 12. Remove 2 oval coil access panel plugs and reinstall into holes on left side of coil access panel and fitting panel.
- 13. Install condensate pan fitting caps (from Step 10) in right side of coil door making sure that cap snaps and seats cleanly on back side of the coil door. Make sure no insulation interferes with seating of cap.
- 14. Reinstall access and fitting panels, aligning holes with tubing connections and condensate pan connections. Be sure to reinstall metal clip between fitting panel and vertical condensate pan.
- 15. Make sure liquid and suction tube grommets are in place to prevent air leaks and cabinet sweating.
- A07566
- Fig. 3 – Slope Coil in Horizontal Left Application (Factory Configuration)
- Fig. 4 – A-Coil in Horizontal Left Application (Factory Configuration)
- Fig. 5 – Conversion for Horizontal Right Applications - Slope Coil
- Fig. 6 – Conversion for Horizontal Right Applications - A-Coil
- Manufactured and Mobile Home Housing Applications
- 1. Secure the fan coil to the structure using field-supplied hardware.
- 2. Allow a minimum of 24" (610 mm) clearance from access panels.
- 3. Recommended method of securing for typical applications:
- a. If fan coil is away from wall, attach pipe strap to top of fan coil using no. 10 self-tapping screws. Angle strap down and away from back of fan coil, remove all slack, and fasten to wall stud of structure using 5/16" lag screws. Typical both side...
- b. If fan coil is against wall, secure fan coil to wall stud using 1/8" (3 mm) thick right-angle brackets. Attach brackets to fan coil using no. 10 self-tapping screws and to wall stud using 5/16" lag screws (Fig. 9).
- Fig. 7 – Removal of Brackets on Modular Unit
- Fig. 8 – Drain Pan Support Bracket
- Fig. 9 – Mobile Home or Manufactured Housing Applications
- Air Ducts
- Electrical Connections
- Line Voltage Connections
- 24V Control System
- Connection To Unit
- Fig. 10 – Wiring Layout Air Conditioning Unit (Cooling Only)
- Fig. 11 – Wiring Layout Air Conditioning Unit (Cooling and 1-Stage Heat)
- Fig. 12 – Wiring Layout Heat Pump Unit (Cooling and 2-Stage Heat with No Outdoor Thermostat)
- Fig. 13 – Wiring Layout Heat Pump Unit (Cooling and 2-Stage Heat for Manufactured Housing)
- Transformer Information
- Heater Staging
- Refrigerant Tubing Connection and Evacuation
- 1. Cut tubing to correct length.
- 2. Insert tube into sweat connection on unit until it bottoms.
- 3. Braze connection using silver bearing or non-silver bearing brazing materials. Do not use solder (materials which melt below 800° F / 427° C). Consult local code requirements.
- 4. Evacuate coil and tubing system to 500 microns using a deep vacuum method.
- Refrigerant Flow-Control Device
- Disassembly
- 1. Use an adjustable wrench with a backup adjustable wrench to loosen Item # 3 (TXV equalizer line).
- 2. For Item #4 - Cut the wire tie and remove the black insulation. Remove the band from around the TXV bulb.
- 3. Cut the wire tie that holds the TXV equalizer line and bulb from the aluminum vapor header tube.
- 4. Remove 2 screws from the TXV bracket. Remove the TXV from the coil unit.
- Assembly
- 1. Mount the TXV bracket and TXV with the 2 screws removed during disassembly.
- 2. Connect Items #1 and #2 (TXV outlet and inlet respectively) and use an adjustable wrench with a backup wrench to tighten each nut. Tighten to between 10 and 20 ft-lbs.
- 3. Connect Item #3 and use an adjustable wrench with a backup adjustable wrench to tighten the flare nut. Tighten to approximately 12 ft-lbs.
- 4. Item # 4 - Reconnect the TXV bulb with a clamp and reinstall insulation around the TXV bulb and vapor tube.
- Fig. 16 – Mechanical TXV Removal
- 5. Use a wire tie to mount the 1/8" TXV equalizer and bulb tubes to the vapor header tube. Make sure that there is insulation between the aluminum vapor tube and copper tube.
- 6. Leak test the TXV fittings, then evacuate and charge the system to the required subcooling per the outdoor unit rating plate.
- Disassembly
- Condensate Drains
- Accessories
- Sequence of Operation
- Start-up Procedures
- Care and Maintenance
- Fig. 22 – Shipping Screws
- Table 2 – Electric Heater Static Pressure Drop (in. wc)
- Table 3 – Airflow Performance (CFM) Wet
- 1. Airflow based upon dry coil at 230V with factory-approved filter and electric heater (2 element heater sizes 018 through 036, 3 element heater sizes 042 through 060).
- 2. To avoid potential for condensate blowing out of drain pan prior to making drain trap: Return static pressure must be less than 0.40 in. wc. Horizontal applications of 042 - 060 sizes must have supply static greater than 0.20 in. wc.
- 1. Airflow based upon dry coil at 230V with factory-approved filter and electric heater (2 element heater sizes 018 through 036, 3 element heater sizes 042 through 060).
- 2. To avoid potential for condensate blowing out of drain pan prior to making drain trap: Return static pressure must be less than 0.40 in. wc. Horizontal applications of 042 - 060 sizes must have supply static greater than 0.20 in. wc.
FJ4: Installation Instructions
Manufacturer reserves the right to change, at any time, specifications and designs without notice and without obligations.
12
NOTES:
1. Airflow based upon dry coil at 230V with factory-approved filter and electric heater (2 element heater sizes 018 through 036, 3 element heater sizes 042 through 060).
2. To avoid potential for condensate blowing out of drain pan prior to making drain trap:
Return static pressure must be less than 0.40 in. wc. Horizontal applications of 042 - 060 sizes must have supply static greater than 0.20 in. wc.
Airflow above 400 cfm/ton on 048-060 size could result in condensate blowing off coil or splashing out of drain pan.
Table 3 – Airflow Performance (CFM) Wet
Ton
(Size)
Blower
Speed
External Static (in. wc)
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0
1-1/2
(018)
Tap 5 754 737 717 694 668 641 605 572 528 481
Tap 4 695 678 655 628 600 573 551 520 479 421
Tap 3 695 678 655 628 600 573 551 520 479 421
Tap 2 643 620 591 557 534 506 477 439 408 378
Tap 1 487 448 428 394 358 325 281 NA NA NA
2
(024)
Tap 5 1021 1003 964 925 876 838 797 761 726 689
Tap 4 936 907 873 805 779 732 696 661 626 591
Tap 3 936 907 873 805 779 732 696 661 626 591
Tap 2 846 831 792 739 702 651 609 548 536 491
Tap 1 746 697 629 567 521 477 446 389 364 326
2-1/2
(030)
Tap 5 1247 1215 1188 1154 1122 1083 1053 1017 971 915
Tap 4 1133 1114 1082 1044 1009 968 924 873 835 785
Tap 3 1133 1114 1082 1044 1009 968 924 873 835 785
Tap 2 1040 997 961 929 883 828 782 725 708 667
Tap 1 896 862 805 740 689 648 597 NA NA NA
3
(036)
Tap 5 1433 1404 1363 1328 1282 1251 1201 1145 1095 1021
Tap 4 1304 1277 1256 1230 1207 1168 1122 1080 1073 983
Tap 3 1304 1277 1256 1230 1207 1168 1122 1080 1073 983
Tap 2 1183 1148 1124 1094 1051 1005 955 901 846 783
Tap 1 1020 995 958 921 881 840 791 735 693 649
3-1/2
(042)
Tap 5 1571 1551 1508 1473 1439 1407 1372 1317 1253 1189
Tap 4 1517 1493 1458 1425 1392 1358 1328 1295 1253 1193
Tap 3 1517 1493 1458 1425 1392 1358 1328 1295 1253 1193
Tap 2 1369 1339 1299 1263 1226 1188 1155 1112 1068 1012
Tap 1 1260 1231 1172 1143 1077 1041 995 949 896 867
4
(048)
Tap 5 1896 1853 1821 1795 1760 1737 1702 1670 1665 1619
Tap 4 1711 1673 1643 1607 1570 1549 1509 1490 1446 1411
Tap 3 1711 1673 1643 1607 1570 1549 1509 1490 1446 1411
Tap 2 1547 1504 1466 1416 1388 1369 1324 1290 1239 1200
Tap 1 1397 1347 1312 1269 1232 1172 1135 1086 1038 989
5
(060)
Tap 5 2109 2067 2043 1996 1967 1928 1899 1848 1812 1766
Tap 4 2109 2067 2043 1996 1967 1928 1899 1848 1812 1766
Tap 3 2109 2067 2043 1996 1967 1928 1899 1848
1812 1766
Tap 2 1901 1868 1825 1785 1737 1710 1662 1620 1584 1521
Tap 1 1583 1557 1499 1451 1392 1358 1313 1259 1194 1138