Instruction manual
WS-PRO2 Weather Station Manual
GT
27176
Page 30 of 61
Figure 19
4.1.2 AC Power Installation
1. The AC power option includes a 120 VAC to 16 VAC step down
transformer. The transformer should be mounted inside a user-
supplied junction box according to local electrical codes.
Dangerous electrical accidents may be avoided by locating the
transformer remotely and burying a low voltage line to the station.
The low voltage will carry up to 500 feet on an 18 AWG power
cable.
2. Shut off 110 VAC power at the main breaker. Connect the primary
leads of the transformer to 110 VAC following instructions provided
with the transformer. Connect a two-conductor cable to the
secondary terminals of the transformer. Route the cable from the
transformer to the ET Enclosure according to local electrical codes.
3. Splice the incoming two-conductor cable to the power cable
provided with the station. Use the direct burial splice kit when
splices are in a valve box or buried.
4. Connect the power plug to the connector marked “Power” on the
back of the enclosure.