User's Manual
Table Of Contents
- PTP 250 User Guide
- Copyrights
- Safety and regulatory information
- Contents
- List of Figures
- List of Tables
- About This User Guide
- Chapter 1 Product description
- Chapter 2 Planning considerations
- Chapter 3 Legal information
- Chapter 4 Reference information
- Chapter 5 Installation
- Chapter 6 Configuration and alignment
- Chapter 7 Operation
- Chapter 8 Troubleshooting
- Testing link end hardware
- Testing when PoE LEDs do not illuminate correctly
- Testing after a lightning strike
- Test flowcharts
- AC LED is off
- AC LED is flashing
- PORT LED is off
- PORT LED is flashing
- Test Ethernet packet errors reported by ODU
- Test Ethernet packet errors reported by managed switch or router
- Test ping packet loss
- Test resistance at the PoE end of the drop cable
- Testing the radio link
- Testing link end hardware
- Glossary
Grounding and lightning protection Chapter 2 Planning considerations
phn-2182_002v000
2-18
May 2011
Protection inside a high rise building
The following protection requirements must be observed inside multi-story or high rise
buildings (Figure 2-6):
• The drop cable shield must be bonded to the building grounding system at the
entry point to the building.
• The drop cable shield must be bonded to the building grounding system at the
entry point to the equipment area.
• An LPU must be installed within 600 mm (24 in) of the entry point to the
equipment area.
Figure 2-6 Grounding and lightning protection inside high building