User's Manual
Table Of Contents
- PTP 250 User Guide
- Copyrights
- Safety and regulatory information
- Contents
- List of Figures
- List of Tables
- About This User Guide
- Chapter 1 Product description
- Chapter 2 Planning considerations
- Chapter 3 Legal information
- Chapter 4 Reference information
- Chapter 5 Installation
- Chapter 6 Configuration and alignment
- Chapter 7 Operation
- Chapter 8 Troubleshooting
- Testing link end hardware
- Testing when PoE LEDs do not illuminate correctly
- Testing after a lightning strike
- Test flowcharts
- AC LED is off
- AC LED is flashing
- PORT LED is off
- PORT LED is flashing
- Test Ethernet packet errors reported by ODU
- Test Ethernet packet errors reported by managed switch or router
- Test ping packet loss
- Test resistance at the PoE end of the drop cable
- Testing the radio link
- Testing link end hardware
- Glossary
PTP 250 User Guide Using the installation wizard
phn-2182_002v000
May 2011
6-23
Step 5: Confirm installation configuration
Step 5 of the Installation wizard is for reviewing and confirming the updated attributes
(Figure 6-19).
I
f any of the attributes are incorrect, select Back to return to previous steps and
update them.
If all attributes are correct, choose one of the following options:
• If antenna alignment tones are not wanted, select Finish. This is the preferred
option before bench testing the units.
• If antenna alignment tones are wanted, select Set Armed and Yes to confirm.
This is the preferred option before site installation and antenna alignment.
Figure 6-19 Step 5: Confirm Configuration page
NOTE
If the IP Address, Subnet Mask or Gateway IP Address of the unit have been
updated to meet network requirements, then reconfigure the local
management PC to use an IP address that is valid for the network. Refer to
Configuring the management PC on
page 6-3.