User Manual

Table Of Contents
7 Installation
56
7 Installation
IMPORTANT Motorola recommends that only qualified personnel undertake the installation of
a PTP 500 Series Bridge solution.
We recommend that the practices and procedures detailed in the Motorola manual R56
"STANDARDS AND GUIDELINES FOR COMMUNICATION SITES" (68P81089E50) be
applied to all new site build activities. For a copy of the manual please see your local
Motorola representative. The manual can be downloaded from the Motorola Intranet site
http://compass.mot.com/go/190860869
.
7.1 Preparation
Before proceeding with the installation you should:
Check the contents of all packages against the parts lists shown in the packing list.
Ensure that you have the correct tools for the job.
Ensure that you are qualified to undertake the work.
Ensure that you have taken the correct safety precautions.
Have completed the site planning as described in Section 6Site Planning”.
7.2 Installation Procedure
The 500 Series installation procedure consists of the following steps:
Mounting the ODUs, Section 7.6Mounting the ODU
s
Connecting up, Section 7.7Connecting Up
Mounting the PIDU Plus units, Section 7.7.9Mounting the PTP 300/500/600 Series
Bridge PIDU Plus
Mounting the Lightning Protection Units, Section 7.7.5Fitting a Lightning Protection
Unit”.
Powering Up, Section 7.7.10Powering Up”.
Aligning the ODUs, Section 7.7.11Aligning the PTP 500 Series Bridge ODUs”.