Specifications
Corrected & Known Anomalies
SPECTRUM Software Release Notice Page 162
2 Save the link by pressing <Return> and then clicking the Create Link
button. The VCL Row Status view displays.
3 Assign traffic parameters for transmit and receive and then click
<Return> to save.
4 Click the Validate Row button and then wait to see that the row
status changes from Not Ready to Active.
5 Return to the Virtual Channel Link Table view to validate that the link
was defined with the assigned traffic parameters.
6 That completes the link definition for the first port to be cross
connected. Now repeat the above steps to complete the link definition
for the other port.
7 When the links are defined correctly for both ports, go to the Virtual
Channel Cross Connect view and follow the instructions in this view
to cross connect the two ports for which you defined links. Cross
connecting establishes the PVC.
8 You should return to the Virtual Channel Link view to ensure that the
PVC has been set properly.
Problem 7: When the Community Name is changed in the Model
Information view of a SmartSwitch 9000 device, the interfaces in the
Chassis Device view do not display a status change but remain in whatever
state they were in when contact was lost with the device.
Solution: The interface number field turns gray to alert you that contact
was lost; however, knowing the previous state of the interface is considered
to be useful information.
Problem 8: The graph in the ATM Performance view seems to display
information incorrectly. For example, the Log and Lin graphs may appear
to show 100% of capacity when the cell rate exceeds a certain value.
Solution: This problem comes about because the graph is used to show
both percentages and rates and has a limitation as to the total cell rate that
can be depicted in the graph. Percentages obviously do not exceed 100%
and the rates on the other hand have a multiplier associated with them