Installation manual

9
INSTALLATION (Continued)
GAS LINE PLANNING
The supply line will need to run vertical through the
heat shield in the center of the fire ring up to where
you will connect it to the gas regulator using a 1/2"
flared flex line (not included). There is a 1" hole in the
heat shield for the gas line (See Figure 5).
BUILDING FIRE RING
WARNING: Failure to position the parts in
accordance with these diagrams or failure to
use only parts specifically approved with this
appliance may result in property damage or
personal injury.
1. Locate a flat even surface to build your fire
ring. See Specifications page 4 for sizing and
Minimum Clearances page 5 when selecting a
location.
2. Use 8 blocks to build the first layer (See
Figure 6). After laying out all blocks, using a
level, verify all the blocks are level. Shim if
necessary.
FOR PROPANE/LP ONLY: On the first
layer, leave 1/8" head joints between
blocks (see Figure 7). Do not grout
between blocks. This will allow air space
for gas to dissipate and not pool in the
event of a gas leak.