Product Overview
11
103859-12 - 8/19
MPO-IQ
Installation & Service Manual
A.  REMOVE CRATE.
1.  Remove all fasteners at crate skid.
2. Lift outside container and remove all other 
inside protective spacers and bracing. Remove 
miscellaneous parts carton.
B.  REMOVE BOILER FROM SKID.
1.  To reduce the risk of damage to boiler jacket, use 
the following procedure to remove from skid, see 
Figure 3:
Step 1.  Boiler is secured to base with (4) 5/16" cap 
screws, (2) in front and (2) in rear of shipping skid, 
see Figure 3. Remove all securing hardware.
Step 2. Place wooden block(s) 12" from rear of 
skid as shown (one piece 4" x 4" x 16" lg. or two 
pieces of 2" x 4" x 16" lg.)
Step 3. Insert 1" Sch. 40 pipe handles through leg 
hole in front and rear legs. Center end of pipe 
on wooden blocks as shown in Figure 3.
  NOTE: Pipe handles should extend a minimum 
of 48" beyond jacket front panel for best leverage.
Step 4. Using the pipe handles, lift boiler until 
adjustable legs are elevated above the deck 
boards.
Step 5. Remove skid from underneath the boiler.
Step 6.  Lower pipe handles until front adjustable 
legs touch floor. If necessary, place wooden 
blocks under front legs before lowering to provide 
hand clearance.
Step 7. To lower rear of boiler, tilt boiler slightly 
forward by pushing on smokebox collar or lift 
pipes protruding through rear legs until wooden 
blocks can be removed (see Figure 3). Slowly 
allow the weight of the boiler to tilt backward until 
rear legs rest on floor.
Step 8. If wood block was placed under front legs, 
lift pipe handles, remove wooden block and lower 
front legs to floor. Remove pipe handles.
CAUTION
 Do not drop boiler. Do not bump boiler jacket 
against floor.
C.  MOVE BOILER TO PERMANENT POSITION by 
sliding or walking.
D.  PROCEDURE TO OPEN, CLOSE AND SECURE  
BURNER SWING DOOR 
  Throughout this manual you will be instructed to open 
and close the burner swing door for various reasons.  
There is a proper and improper method to closing and 
securing the burner swing door opened for inspection, 
cleaning or field service.
1.  TO OPEN BURNER SWING DOOR 
  (see Figures 4A and 4B).
Step 1. Loosen but do not remove left side 
latching hardware (3/8" x 1-3/4" lg. tap bolt).
Step 2.  Loosen and remove right side latching 
hardware (3/8" x 1-3/4" lg. tap bolt and 
washer).
Step 3.  Remove left side latching hardware (3/8" 
x 1-3/4" lg. tap bolt and washer).
Figure 3: Packaged Boiler Removal from Skid
2 Packaged Boiler Assembly - Trim & Controls
!