Installation guide

1-11
Delivery
Inspecting Internal Components and Cabling
A thorough visual inspection of internal components and cabling should now be carried out
before powering up the server.
CAUTION:
If the inspection indicates an unacceptable safety condition, the condition must be corrected
before powering up the server.
1. Visually check internal cables for damage.
2. Visually check system components for damage.
3. Manually check internal cable connections.
4. Visually check external power cables for damage.
Note:
If you need to check CSS Module components, refer to the Maintenance and Service Guide.
For guidance with cabling, see Cabling Guide, 86 A192ER.