Installation guide
1-7
Delivery
General Recommendations
Bull NovaScale Servers are delivered rack-mounted and pre-cabled in one or more high or
low cabinets, according to the version chosen.
Site preparation must be completed by the pre-arranged delivery date. Any delay due to
non-completion of the site by the pre-arranged date will be considered as the Customer's
responsibility.
The server is delivered 24 hours in advance of the scheduled installation date. On arrival, it
must be placed, in its packing, in the Computer Room so that it reaches room temperature
before powering up (optimum operating temperature = 22° C +
3° C, hygrometry = 50% +
5%).
CAUTION:
It is mandatory for the server to be transported vertically. Servers are extremely heavy and
require the use of an elevator. The Data Processing Site manager must allocate enough
personnel to ensure safe handling.
Use the Packing Slip to check the number and condition of the shipping boxes prior to
unpacking.
The server is delivered with a box labeled Open Me First containing all the data and items
required for installation.
Warning:
To avoid condensation and incorrect handling, the server must be removed from its packing
by authorized Service personnel ONLY, on the scheduled installation date.