Installation guide
1-14
Installation Guide
Inspecting Internal Components and Cabling
The server is delivered pre–tested, pre–cabled, and ready for use.
A general preliminary visual inspection was carried out before unloading the cabinet from
the pallet. Now that the cabinet has been secured into place in the Computer Room, a
thorough visual inspection of internal components and cabling should be carried out before
refitting side covers and doors.
CAUTION:
If the inspection indicates an unacceptable safety condition, the condition must be
corrected before powering up the server.
1. Visually check internal cables for damage.
2. Visually check system components for damage.
3. Manually check internal cable connections.
4. Visually check external power cables for damage.
Note:
If you need to check CSS Module components, refer to the Maintenance and Service
Guide, 86 A7 90EF.
For guidance with cabling, see Checking Server Cabling, on page .
Important:
Once the inspection is complete, side covers and doors must be refitted before
powering up the server. See Refitting Side Covers, on page 1-20, Refitting the Rear