Installation guide

1-6
Installation Guide
Inspecting the Cabinet
A preliminary visual inspection must be performed once the server has been unpacked and
before unloading the cabinet from the pallet.
CAUTION:
If the inspection indicates an unacceptable safety condition, the condition must be
corrected before powering up the server.
1. Check that the server delivered is compliant with the Purchase Order.
2. Check covers and doors for sharp edges, damage or alterations.
3. Check the correct fit of covers and doors.
4. Open the front and rear doors.
Note:
Unlock the front door with the key, pull the handle forwards and upwards to disengage the
lock.
5. Check for internal damage, alterations and obvious safety hazards such as broken wires,
sharp edges, or broken insulation.
6. Check internal cables for damage.
7. Check for dirt, water, and any other form of contamination inside the cabinet.
8. Check the voltage label on the back of the cabinet to ensure that it matches the voltage
at the power outlet.
9. Check external power cables for damage.
10. Check correct closure of front and rear doors.
Note:
Server components and configuration may differ according to the version chosen.