Installation Instructions

11
System start-up
Logano G315 – 6 720 817 939 (2016/04)32
Removing flue gas baffles
For boilers with 7 – 11 boiler sections (819 – 1,553 MBH or 240
455 kW) an increase of the flue gas temperature can be achieved
through pair-wise removal of the upper or lower flue gas baffles.
11.6 Commissioning log
The Logano G315 can be used with an oil- or gas-fired burner. Fill in the
commissioning log for the appropriate type of oil or gas burner carefully.
Sign all start-up work as completed and enter the relevant date.
Commissioning operations Individual steps Comments (signature)
1. Perform leak test of the entire system
2. Fill the heating system with water page 31
3. Purge the heating system
4. Perform the leak test if the boiler was assembled on-site page 17
5. Record the filling water quantity and composition in the
operator’s log (included with the technical documentation).
6. Check position of flue gas baffles page 20
7. Check the fuel line for leaks
8. Start up the control panel page 31
9. Initial burner start-up See burner
documentation
10. Check the flue gas temperature page 31
11. Check vent pipe for leaks
12. Check the boiler on the hot gas side for leaks
13. Enter the fuel used in the table provided in the operating
instructions
14. Inform the owner and operator and hand over technical
documentation
15. Confirm properly-completed commissioning
Company stamp/signature/date
Table 13