Installation Instructions
7
Boiler block assembly
Logano G315 – 6 720 817 939 (2016/04)20
7.8 Installing fittings and burner door
Next step in the assembly process is to install the burner door and draft
diverter. The pre-assembled boiler comes with these components
already installed.
7.8.1 Positioning the draft diverter
KM ropes (Fig. 28, [1]) are used to seal the connections between the
boiler and the draft diverter (Fig. 28, [2]).
▶ Coat the packing grooves with adhesive (primer).
▶ Push the KM ropes firmly into the groove. Insert the sealant rope in
such a way that the joint is in the side part of the groove (Fig. 28,
[3]).
▶ Place the draft diverter onto the two threaded studs on the rear
section (Fig. 28, [4 and 5]) and secure using washers and nuts.
Fig. 28 Fitting the draft diverter
7.8.2 Screwing cleanout cover onto rear section
Fig. 29 shows the fully equipped rear section with the cleanout covers
on the draft diverter (Fig. 29, 1 and 2]) and the cleanout covers on the
rear section (Fig. 29, [3 and 4]).
All cleanout covers are factory-fitted.
Fig. 29 Rear section with fittings installed
7.8.3 Inserting the flue gas baffle plates
▶ Take flue gas baffles from the crate and insert into the flue gas
passages as indicated by their inscription ( Fig. 30 and
Tab. 10).
Fig. 30 Flue gas baffle plates
7.8.4 Fitting burner door panel
In the factory, the burner door is mounted with the hinges on the right
hand side (Fig. 31, [4 and 6]). For left-hand closing, remove the hinges
accordingly on the left-hand side of the burner door.
▶ Screw the hinge pins (Fig. 31. [1 and 3]) to the front boiler section
with 2 M 12 x 50 machine screws in each case. This is shown in
Fig. 31 for the right-hand closing version. For left-hand closing,
secure hinge pins accordingly on the left-hand side.
▶ Affix Ø 18 mm diameter GP cord in the front section using adhesive.
The sealant rope joint should be located at the side (Fig. 31, [2]).
▶ Hook the burner door with the hinge lobes into the hinge pins.
In pre-assembled boilers, the flue gas baffles are already
fitted
▶ Remove the cardboard transport protectors from the
pre-assembled boiler.
Number of
boiler
sections
Number of
flue gas
baffle plates
Length of flue gas
baffle plate in
inches (mm)
Installation directions
on the flue gas baffle
plate ( Fig. 30)
5 4 14-11/64 (360) top right
top left
bottom right
bottom left
6 – 7 4 17-21/64 (440)
8 4 14-11/64 (360)
9 4 7-7/8 (200)
Table 10