Owner manual

5 Putting into operation
33 SpeedExtractor E-916/E-914 Operation Manual, Version D
5 Putting into operation
This chapter describes the installation of the SpeedExtractor and gives instructions on initial start-up.
NOTE
Inspect the instrument for damages during unpacking. If necessary, prepare a status report imme-
diately to inform the postal company, railway company or transport company. Keep the original
packaging for future transport.
5.1 Installation site
Put the instrument on a stable, horizontal surface. Consider the maximum product dimensions and
weight. Obtain the environmental conditions as described in section 3.4, technical data.
Installation prerequisites:
Do not place any objects on top or below the instrument or parts of it.
The instrument must be installed with 5 cm clearance to any other objects or walls to allow suf-
ficient cooling.
Do not store containers, chemicals or other items behind the instrument.
!
WARNING
Death or serious injuries by use in explosive environments.
Do not operate the instrument in explosive environments
Do not operate the instrument with explosive gas mixtures
Before operation, check all gas connections for correct installation
Directly withdraw released gases and gaseous substances by sufficient ventilation
!
CAUTION
Risk of minor or moderate injury by heavy weight of the instrument.
Consult three further persons to transport the instrument
Do not drop the instrument
Place the instrument on a stable, even and vibration-free surface
Keep limbs out of crushing zone
NOTICE
Risk of instrument damage by liquids or mechanical shocks.
Do not spill liquids over the instrument or its components
Do not move the instrument when it is loaded with sample liquid
Do not drop the instrument or its components
Keep external vibrations away from the instrument
Safely attach the instrument to the bench in earthquake prone regions
Do not operate the instrument without the protection cover installed at the front