Instruction Manual

5 Putting into operation
20 Melting Point M-565 Operation Manual, Version D
5 Putting into operation
This section describes the installation of the Melting Point M-565 and gives instructions for initial start-
up.
NOTE
Inspect the instrument for damage during unpacking. If necessary, prepare a status report imme-
diately to inform the postal company, railway company, or transport company. Keep the original
packaging for future transport.
5.1 Installation site
Place the instrument on a stable, horizontal surface adequate for the maximum product dimensions.
It is advisable to place the instrument in a fume hood due to the fact that it will be used to measure
chemical substances. For safety reasons and to ensure sufficient cooling in the electronic compart-
ment, of the unit must be placed at least 30 cm away from rear walls or other objects. No containers,
chemicals, or other appliances should be placed behind the unit.
NOTE
Do not expose the instrument to direct sunlight or very high illumination. This could influence the
automatic detection process.
General hazards arise from:
Mixtures of unknown composition or contaminations
Combustible gases or solvent vapors in the immediate vicinity of the unit
Damaged glass components
Insufficient distance from back of the unit to the wall
Burning by touching hot parts of the heater
5.2 Commissioning
5.2.1 Unpacking and installation
Unpack the instrument and place it on a table. Remove the packing, and make sure that the
following parts are installed: