User's Manual
Table Of Contents
- 1 Introduction
- 2 Safety
- 3 System Overview and Unit Description
- 3.1 System Overview
- 3.2 Host Unit Description
- 3.3 Remote Node Description
- 4 System Installation
- 4.1 Unpacking and Inspection
- 4.2 Installation Preparation
- 4.3 Host Unit Installation
- 4.4 Remote Node Installation
- 4.5 Installation Final Inspection
- 4.6 System Test
- 5.1 Accessing EMS Local GUI
- 5.2 Navigating the EMS Local GUI
- 5.3 Installation & Configuration
- 5.4 System Tuning
- 5.5 Monitoring and Alarms
- 5.6 System Upgrade
- 6 Maintenance
- 7 Terms, Acronyms & Abbreviations
- 8 Packing List
mBSC2500U-005-RUCM11
MBSC2500U-005-RUCM11 April 15, 2013
Page 27
4.3 Host Unit Installation
4.3.1 Rack Mounting
The Host Unit is a 19” 4U equipment shelf. When loading the Host Unit in a rack, make sure the mechanical
loading of the rack is even to avoid a hazardous condition. The rack should safely support the combined
weight of all the equipment and be securely anchored. Installing the Host Unit in a room with sufficient air
circulation is recommended as the maximum ambient temperature for Host Unit is 60°C.
Use the following steps to install the Host Unit in the equipment rack:
1. The Host Unit is built with mounting bracket installed for 19” rack installation.
Figure 20 Mounting Brackets for 19” Rack Installation
2.
Position the host unit in the designated mounting space in the rack as shown below.
3. Secure the mounting bracket to the rack using the four mounting screws provided.