4.4 Remote Node Installation
The remote unit is a 19” 4U equipment shelf. When loading the remote unit in a rack, make sure the
mechanical loading of the rack is even to avoid a hazardous condition. The rack should safely support the
combined weight of all the equipment and be securely anchored. Installing the remote unit in a room with
sufficient air circulation is recommended as the maximum ambient temperature for remote unit is 60°C.
remote unit install as same as HU device. Please refer to chapter 4.3.1.
4.4.1 Cable Connections
Attention
All the power switches must be switched off before cable installation.
Avoid bundling signal cable and grounding cable/power cable, keep them separate.
The power cable and RF inter-connection cables are supplied.
Check open and short circuits before installing the power cable.
4.4.1.1 Coaxial Cable Connections
The simplex low-power RF interface between the RTM enclosure and the single-band RUM enclosures is
supported through RF QMA female connectors mounted on the enclosure panel. The duplex high-power RF
interface between the single-band RU enclosures and the BCM enclosure, and to the service antennas, is
supported through Nfemale connectors mounted on the enclosure panel.
4.4.1.1.1 BCM to Single-band RU
To connect the coaxial cable between BCM enclosure and single-band RU enclosure:
1. Obtain the required lengths of high performance, flexible, low loss 50 coaxial communication
cable for all coaxial connections.
2. Route the RU ANT and BCM N connector coaxial cable between the BCM enclosure and
single-band enclosure interface and cut to the required length.
3. Dress and secure cable.