Specifications

Hercules Boiler Model 11
Commission/Handover
Ensure loose parts are fitted in accordance with the instructions for “Assembly” given
above.
On completion of the installation allow a suitable period of time for any fire cement
and mortar to dry out, when a small fire may be lit and checked to ensure the smoke
and fumes are taken from the stove up the chimney and emitted safely to
atmosphere. Do not run at full output for at least 24 hours.
On completion of the installation and commissioning ensure that this installation and
operation manual for the stove is left with the customer. Ensure to advise the
customer on the correct use of the appliance with the fuels likely to be used on the
stove and warn them to use only the recommended fuels for the stove.
Advise the user what to do should smoke or fumes be emitted from the stove. The
customer should be warned to use a fireguard to BS 6539 in the presence of
children, aged and/or infirm persons. Advise the user not to fit an extract fan in the
same room as the stove as this can cause the stove to emit fumes into the room.
Insure the boiler system is fully operational and performs to the design specification.
Insure any safety features are fully operational.
Also check the following points and insure they have been addressed:
1. Flue draught is correct
2. Flue draught measurement =
3. Flue soundness
4. Flue operation correct
5. Flue data plate completed
6. Appliance smoke tested
7. Hearth fitted to current standards
8. Correct air brick/ventilation installed
9. Ensure the heating system is functioning correctly