Installation guide

20 Brocade NetIron CES 2000 and NetIron CER 2000 Hardware Installation Guide
53-1001834-01
Installation precautions
2
Installation precautions
Follow these precautions when installing the unit.
DANGER
Risk of explosion if battery is replaced by an incorrect type. Replace the battery only with the
same or equivalent type recommended by the manufacturer. Lithium battery is a long life battery
and it is very possible that you will never need to replace it. However, should you need to replace
it, do not dispose of the battery along with household waste. Contact your local waste disposal
agency for the address of the nearest battery deposit site.
TABLE 6 Summary of installation tasks
Task
number
Task Where to find more information
1 Ensure that the physical environment that will host the device
has the proper cabling and ventilation.
“Installation site preparation” on
page 24
2 Optionally insert a second or redundant power supply. If you
need to install a power supply, it may be easier to install it
before mounting the device, although the power supplies are
“hot swappable”, and can be installed or removed after the
device is mounted and powered-on.
“Redundant power supply
installation” on page 25
4 Install the Brocade device in an equipment rack. “Device installation” on page 31
5 Once the device is physically installed, plug the device into a
nearby power source that adheres to the regulatory
requirements outlined in this manual.
“System power” on page 36
6 Verify that the system LEDs are registering the proper LED
state after power-on of the system.
“Operation verification on page 37
7 Attach a terminal or PC to the Brocade device. This will enable
you to configure the device through the Command Line
Interface (CLI).
“PC or terminal attachment” on
page 39
8 No default password is assigned to the CLI. For additional
access security, assign a password.
“Password assignment” on page 41
9 Before connecting to the device, you need to configure an
interface IP address to the subnet on which it will be located.
Initial IP address configuration is performed using the CLI with
a direct serial connection. Subsequent IP address
configuration can be performed using the command line
interface.
“IP address configuration” on
page 42
10 Once you power on the device and assign IP addresses, the
system is ready to accept network connections.
“Device connection” on page 45
13 Secure access to the device. NetIron Configuration Guide