Installation Guide
20
• Torque circuit breaker connections to 45 in-lb [5 Newton meter].
Generator ACSystem Connection
A single-phase, three-wire AC connection system is used
in the generator. The stator assembly consists of a pair
of stationary windings with two leads brought out of each
winding. The junction of leads 22 and 33 forms the neutral
lead, as shown schematically and as a wiring diagram.
NOTICE Neutral is not bonded to ground at generator.
NOTICE Generator must be used with only an UL
approved transfer switch that is compatible with the
generator.
Grounding the Generator
Unless mandated by local code, additional chassis grounding
to earth at the generator is not required. Any grounding
at generator must use metal piercing lock washers (or
equal), listed terminals installed per terminal supplier’s
instructions, and comply with national electrical codes and
local requirements.
Power Connections from the Generator to the
Transfer Switch
 WARNING
Failure to isolate generator from utility power could
result in death or serious injury to electric utility workers due
to backfeed of electrical energy.
• Use a listed transfer switch to connect to a building
electrical system.
Utility Circuit Connection
240V Utility leads must be routed in conduit. The 240V Utility
leads deliver power to the generator’s circuit board, optional
battery warmer and optional oil warmer. This power also
charges the battery. When the power on these leads is lost,
the generator will start. Using the installer-supplied minimum
300V, 14 [2.5 mm2] AWG wire, connect each control circuit
terminal in the generator (25 and 26) to the fuse block in the
automatic transfer switch.
Generator Power Connection
Using the installer supplied minimum 300V wires and the
table located in theElectrical Field Connectionssection,
connect generator power output L1, L2, neutral (N), and
ground to the corresponding L1, L2, neutral (N) and ground in
the transfer switch.
NOTICE Refer to the National Electric Code for correct
electrical field connections and wire size calculations.
Final Installation Considerations
Engine Oil
NOTICE Any attempt to crank or start the engine before it
has been correctly filled with the recommended oil will result
in equipment failure and service codes.
• Refer toMaintenancein theOperationsection of this
manual for oil fill information.
• Damage to equipment resulting from failure to obey this
instruction will void the engine and generator warranty.
This engine is shipped from the factory pre-run and filled
with synthetic oil (API SJ/CF 5W-30). This allows for system
operation in a wide range of temperature and climate
conditions. Before starting the engine, check the oil level as
described in theMaintenancesection of this manual.
The use of synthetic oil does not alter the required oil change
intervals described in theOperationsection of this manual.
Not for 