Suboor Installaon
• Installaon on plywood and wood substrates: DO NOT install over parcleboard.
1. Suboor should be 3/4” or thicker plywood to be installed over 16” on center joists.
2. Lay plywood so grained outer plies are at right angles to joists; adjacent rows should be
staggered four feet and nailed with 7D or larger nails, every 6” along each joist.
3. Re-nail old oor where squeaks occur and sand down any high spots and install the new planks
perpendicular to the old boards, or overlay with ¼” plywood underlayment.
4. Leave a 1/8” gap at edges and nail every 6” at edges, and every 12” in both direcons and
through the interior of each plywood sheet with 7D or larger nails.
5. The plywood or wood substrates should have a moisture content within 2 percent of that of the
acclimated wood ooring.
• Installaon on concrete slabs
1. Concrete slabs must have at least ¾” of plywood and 6 mil polylm vapor-barrier aached, per
the NWFA guidelines for nail-down suboors on concrete.
2. Use mechanical fasteners including; powder-driven pins, pneumac driven nails, screws,
deformed pins, or other concrete-suitable applicaon.
3. Allow at least 3/4” for expansion around all vercal obstrucons.
4. Allow 1/8” space around staggered panels.
5. Fasten starng in the center and moving out, to prevent bowing.
6. Then fasten 2” from the edge at 6”-8” intervals along the perimeter of the sheet and then at
least one fastener spaced every 12” across the interior of the panel.
Center Line Layout Method
• Using the trammel point method nd the middle of the room and snap a line down the center in
the longest direcon.
• Using wood screws, install a starter board along the line.
• Now nail a rst row of ooring along the starter board, ensuring that the starter board does not
move during the process. The grove edge should be lined up against the starter board.
• Then drill and nail the rst three rows through the tongue. Top nails should not be used.
• A blind nailer should be used to install the remaining rows of ooring.
• Once the rst direcon is complete, remove the starter board and repeat in the other direcon.
Note that this will require the use of a spline or slip tongue to join the groove edges and reverse
direcon.