Installation Instructions
Supplies required for installation:
• (6)
3
/8" wall anchors, bolts and washers to mount bowl to wall (min. pull-out force of 1,000 lbs.)
• ½" nominal copper tubing hot and cold or tempered supply piping
• 1½" drain piping and P-Trap (available from Bradley, p/n 269-1697)
• 110 VAC power source for 110/24 VAC plug-in transformer supplied
• OPTIONAL TRAP COVER: ¼" wall anchor, bolt and washer to mount trap cover to wall
• OPTIONAL: Bradley recommends installing an electrical cut-off switch to the unit (this feature prevents
accidental water delivery during regular maintenance and service)
Step 1: Rough-ins
NOTE: Refer to Figure 1 below and Figure 2 on page 4 for Express
®
Crescent
®
Lavatory System rough-ins and
dimensions.
1. Rough in ½" nominal copper tubing hot and cold supply lines and 1½" NPT drain waste connection
through wall at dimensions shown in Figure 1.
IMPORTANT: Flush all the water supply lines before making con nec tions. Debris in supply lines
will cause the valves to malfunction.
Figure 1
* ADJUSTMENTS TO VERTICAL DIMENSIONS FOR VARIOUS RIM HEIGHTS
Rim Height Application Adjustment
34" Adult Height ADA, TAS Adult Height TAS Adult Height None, as shown
32" TAS Ages 11 thru 14 or 15, Grades 6 thru 8 or 9 Subtract 2"
30" TAS Ages 4 thru 10 or 11, Grades: Pre-K thru 5 or 6 Subtract 4"
& Proposed Juvenile Height ADA
24" Preschool (required by some local codes) Subtract 10"
Standard Height Mounting
6½"
(165)
(mm)
2"
(51)
23¾"
(603)*
½" Nominal Copper Tubing
Hot and Cold Supplies
Stub Out 2" (51)
Floor
Centerline of
Fixture
½" NPT Drain
Stub Out 2" (51)
Trap Cover
(Optional)
25
5
8"
(651)*
Rim
Height
34"