Technical data

INSTALLATION INSTRUCTIONS - Page 14
LIFTING THE BOILER
Lift the boiler onto its mounting bracket.
FIG. 15
FIG. 16 TRANSPORTATION FOOT
Locate the studs on the air duct flange through the boiler
casing and secure using four wing nuts (accessory pack F).
Position boiler on its mounting bracket so that the sides of
the boiler line up with the reference lines ‘C’ on the rear wall.
Undo the two screws securing the transportation foot and
discard foot. Vertical alignment with rear wall can be
corrected using the adjustment screws at the rear of the
boiler. See FIGS. 16 & 17.
FIG. 17 SECURING BOILER
FIG. 18 FLUE ELBOW EXTENSION
Rotate the left hand adjustment screw to align one of the
holes in the base plate with hole ‘D’ in the wall. Working
through the hole in the leg, secure the base plate to the wall
using the screw from accessory pack D. Make good the wall
surface around the flue terminal. Fit optional terminal wall
plate if required.
When side fluing, slide the elbow extension onto the elbow
and ensure that it is pushed on fully. Engage the screw from
accessory pack ‘C’ into the pre-drilled hole in the elbow
extension and screw fully home. The screw which is self
drilling will pierce the elbow and secure the extension to the
elbow.