Instructions / Assembly
No Diving or Jumping. Observe all Safety Rules
1-28
GENERAL INSTRUCTIONS - YARDMORE OVAL POOLS
GROUND PREPARATION
Sec on
1
D. CONT. GROUND PREPARATION FOR THE BUTTRESS
Even number of buttresses:
a. If your oval pool contains an even number of
buttresses, measure from the center line out 21”.
Position the buttress temporarily off the straight
center line from the middle. (Image 19)
b. Trace around the buttress and dig a trench. Dig the
trench 3 to 5 inches deep by 10 inches wide and the
length of 52 1/2 inches long. (Image 20)
c. The bottom plates for the straight section must be
at the same level with the crushed stone. If you do
not put crushed stone, understand that the bottom
plates all around the pool must be at the same
level. The warranty will void if you do not comply
with this requirement.
d. Apply crushed stone at 1 inch, then compress. Place
a concrete block of 2 inches at each end of the
trench.
e. Once the block is installed, measure the depth of
the trench, it must be 2 inches deep. Make sure the
block is level by using an optical level. Ensure that
both blocks are at the same level.
f. Place the buttress structure on the blocks and
ensure that each buttress is parallel to each other.
(Image 21)
Important Note:
This first buttress that you install will be the reference
to install the remaining buttresses, therefore ensure that
measurments and placements are exactly where they
need to be.